Temple Construction Updates
August - 2025
rightarrow Highlights:
1. Boundary Wall : Iron fabrication work is in progress. Despite delays due to rains and festivals, the West side is near completion, and other sides have started. 2. Radha Krishna Temple Site (East): Stones are mostly cleared. Area prepared for Kitchen construction in Phase 1, which will serve as the temporary temple. 3. Pancha Tattva Block (West): Stone blasting completed; shifting of stones is in progress. 4. Seva Office (South): Pillars erected for ready-made container. This will house the Seva Office to serve devotees with donation receipts, drawings, and meeting space. 5. Temple Drawings: Work is ongoing with Stapathi Prasad Garu, Architect Kiran Prabhu, under the guidance of HH Bhakti Padma Swami Maharaj. 6. Temple Lease: Extension to 22 years approved by the Minister.